- Project name: Giang Dong bridge
- Location: Lao Cai City
- Year of commencement: 2014
- Year of completion:2015
Highlights of the project
Giang Dong Bridge is a reinforced concrete box girder bridge, constructed by the balanced cantilever casting method. The span diagram is 55 + 90 + 55m. The main bridge length is 200m. The total width of the bridge cross section is 14m
Description of advanced science, technology and software application
The main bridge is constructed by balanced cantilever technology with 3 continuous cantilever spans of 90m and a total length of 200m.
The main bridge was modeled and calculated by RM V8i software, local calculated by Midas FEA; pile foundation was caculated by FB Pier. In the construction phase, control and calculation of camber by RM V8i.