cau_CAMHAI_2
  1. Project name: Cam Hai Bridge on Hạ Long – Vân Đồn expressway project
  2. Location: Cam Hai dist., Cam Pha city, Quang Ninh province
  3. Year of commencement: 2015
  4. Year of completion:2017

Highlights of the project

The main bridge is a box-girder bridge constructed by the of balanced cantilever method. The span diagram is 55 + 90 + 55m. The main bridge length is 200m. The total width of the bridge cross section is 24.25m.

Description of advanced science, technology and software application

The main bridge was modeled and calculated by RM V8i software, local calculated by Midas FEA; pile foundation was caculated by FB Pier. In the construction phase, control and calculation of camber by RM V8i.