Highlights of the project
The main bridge is a box-girder bridge constructed by the balanced cantilever method. The span diagram is 48 + 72 + 48 m. The main bridge length is 168m. The total width of the bridge cross section is 24.5m.
Description of advanced science, technology and software application
The main bridge was modeled and calculated by RM V8i software, local calculated by Midas FEA; pile foundation was caculated by FB Pier. In the construction phase, control and calculation of camber by RM V8i.